Your location: Home > The ball mill installation test run
News

The ball mill installation test run

Date: 2014-7-29 18:16:55 Read: 3469 times

Commissioning: 
Ball mill installation is complete, after inspection, the empty test run can be achieved. The ball mill of ball mill in the test run by skilled operators, ball mill and strictly abide by the safety operation procedures. 
(a) continuous operation of idle running time not less than 12-24 hours a day, found that the problem should be resolved in a timely manner during operation. 
(2) the idle running of commissioning can be normal load test run. The load test run in every phases. Load operation shall be carried out according to the condition of discharge in the feed, avoid unnecessary grinding ball and the cylinder liner and damage. 
1, add appropriate material, and a third the number of steel ball (see the largest amount with ball mill assembly drawing) test run 12 to 24 hours. 
2, join to two-thirds of the number of steel ball works 24 to 48 hours. 
3, according to the ball mill discharge conditions, production of qualified products, with reference to the same kind of ball-mill machine actual loading quantity, determine the ball loading quantity of the ball mill machine, step to less than 72 hours of test run. 
(3) the increase of the load and test run of the length of time, with the size of the gear and gear reducer of the running-in condition (temperature, noise, tooth contact, etc.) as a basis for sure. In front of the tooth surface contact precision did not meet the design requirements, shall not operate at full capacity. (4) commissioning of cooling and lubrication system should be working properly. Main bearing, bearing, reducer temperature should be normal. 
(5) into the two-thirds of the number of steel ball test run 24-48 hours later, should check and tighten all bolts again. 
(6) the commissioning work should earnestly each record. 
CATEGORY
PRODUCTS
国产寡妇亲子伦一区二区三区四区 | 亚洲AV无码乱码国产精品牛牛 | 国产精品久久久久久久久久影院 | 欧美一区二区三区三州AAAAA | 国产乱码精品一区二区三区中文 | 国产精品白嫩美乳在线播放量大 | 夜夜穞天天穞狠狠穞牛牛影视 | 91精品国产一区二区三区蜜臀 | 久久99精品久久久久久园产越南 | 久久无码人妻丰满熟妇区毛片 | 黄色视频在线免费无码观看 | 潘金莲一级婬片AAAAA免费看 | 日本无码人妻波多野结衣杨思敏 | 精品久久人人爽人人玩人人妻 | 国产精品186在线观看在线播放 | 玩丰满高大邻居人妻无码牛牛影视 | 红桃ht447vip国产 | 一本一道人妻久久久久久中文字幕 | 国产高清无码免费视频 | 蜜桃AV电影免费播放 | 久久久精品A片免费观看农村妇女 | 高潮毛片又色又爽免费 | ,国产精品久久久久老太8爱 | 91久久久无码精品不卡A片直播 | 亚洲精品无码一级毛片AA片漫蛙 | 红桃视频成人无码在线观看 | 1000部啪啪未满十八勿入免费88AV | 久久美女视频在线 | 国产欧美精品久久久一区二区三区 | 老司机香蕉a片在线观看 | 亚洲AV无码在线看 | A国产三级三级无码V片 | 日本公妇乱婬A片免费看网站下载 | 免费涩涩18 网站入口 | 亚洲精品秘 一区二区三区蜜桃久 | 強行糟蹋人妻HD中文 | 黄色免费网站在线观看 | 夜夜躁狠狠躁日日躁麻豆护士 | 91一区二区三区四区在线观看 | 成人网站免费观看www打球中国 | 2018日日干夜夜爽 |